Copenhagen Metro

About Case

The Challenge

Encountering an old bridge structure in the same location as an underground station resulted in a construction delay of two years. The Employer took the position that the Contractor should have been fully aware of the possibility of encountering bridge remains at that location. Of course the Contractor took the position that he could not have known how much of the old bridge structure remained and to what degree it would impact on the method of working and time needed to deal with the issue..

The Solution

The arbitration tribunal found, with respect to time, in favour of the Contractor for whom we acted as expert witness at the hearings.

The Result

We were able to provide our opinion in support of the whole time claimed with detailed programme analysis and relying on daily site records.